Cascade Charter Township Ordains:
Section I. An Amendment to The Cascade Charter Township Zoning
Ordinance
The application received from Robert Grooters Development Company
or their assigns (hereinafter referred to as the "Developer"), for
Planned Unit Development designation for the 5251 – 36th Street
Project (hereinafter referred to as the "Project") was recommended by
the Cascade Charter Township Planning Commission for approval on
October 5, 1992. The Project is recommended for rezoning from I,
Industrial to PUD, Planned Unit Development permitting the removal of
the non-conforming status on a building which has been historically
used as an office building. This recommendation requires an amendment
to the Cascade Charter Township Zoning Ordinance and Zoning Map to
incorporate the Planning Commission’s recommendation and the Cascade
Charter Township Board of Trustees action on October 14, 1992.
Section II. Legal Description
The legal description of the Project is as follows:
That part of the SE 1/4, Section 18, T6N, R10W, Cascade Township,
Kent County, Michigan, described as: BEGINNING at the S 1/4 corner of
Section 18; thence N 01 degrees 39’17"W 935.0 feet along the N-S ¼
line of Section 18; thence N 88 degrees 16’56"E 641.00 feet along the
South line of Foremost Industrial Park No. 2; thence S 01 degrees
39’17"E 395.00 feet; thence N 88 degrees 16’56"E 24.0 feet; thence S
01 degrees 39’17"E 540.0 feet; thence S 88 degrees 16’56"W 665.0 feet
along the South line of Section 18 to the place of beginning. Subject
to highway R.O.W. over the Southerly 50 feet thereof. This parcel
contains 14.056 Acres, including highway R.O.W.
Section III. General Provisions
The following provisions shall hereby apply to the Project, in
addition to those Provisions outlined in Chapter 14 of the Cascade
Charter Township Zoning Ordinance (Ordinance No. 11 of 1988, as
amended) and the Cascade Charter Township Subdivision Ordinance
(Ordinance No. 1 of 1978, as amended).
Section IV. Purpose
The Project occupies approximately 14.056 acres of land that is
currently being used for offices and data processing. The proposed use
for the Project is to continue those uses and some limited accessory
uses commonly allowed in the "O", Office zoning district.
The provisions of this Ordinance are not intended as s substitute
for the Cascade Charter Township Zoning Ordinance and the General
Development Plan, nor do they in any way relieve the Developer from
obtaining all approvals and permits required by the township except as
provided herein. In the event that a development issue or site plan
element is not addressed by this Ordinance, the specifications and
requirements of the Cascade Charter Township Zoning Ordinance shall be
enforced.
Section V. Permitted Uses
The permitted uses for the 5251 – 5253 – 36th Street
Project are as follows:
A. Executive and administrative offices, data processing
centers and business offices such as real estate, insurance, and
non-profit organizations.
B. Medical and dental laboratories.
C. The following personal service establishments when located
within an office building:
1. Cafeterias or food services operated during normal
business hours and primarily catering to on premises
employees; and
2. Other personal service establishments including child
care and day care and day nurseries which are compatible with,
subservient to and which cater to, on premises or neighboring
businesses and employees.
And provided that such personal service establishments are:
a. Limited to basement and ground floors of the building;
b. The total gross floor area collectively occupied by
personal service establishments shall not exceed ten (10)
percent of the gross floor area of the building’s ground
floor; and
c. The gross floor area occupied by any single personal
service establishment shall not exceed ten (10) percent of the
gross floor area of the building’s ground floor.
D. Accessory structures and uses customarily incidental to the
uses permitted in this Section, subject to the provisions of
section 4.08 of the Zoning Ordinance.
Section VI. Design Guidelines, Requirements and Limitations
The development of all permitted uses within the Project shall
conform to the site plan and/or Mortgage survey dated May 3, 1991 and
approved by the Township Board on October 14, 1992. No alternations,
expansions or additions may take place to the Premises without an
amendment to this Ordinance.
A. Signs
All new signs (type, size, etc.) for the Project shall comply
with the Cascade Charter Township Sign Ordinance, as amended.
B. Utility Easements
In the event that additional utility easements are needed to
serve the Project, the Developer shall provide all necessary
easements to the appropriate utility provider without cost. In the
event the Township requires additional sewer and water service
easements in the future, the Developer shall provide them at all
reasonable locations. Said easements shall be recorded with the
Kent county Register of Deeds and provided to each utility
provider for their records.
Section VII. Performance Guarantee
To insure compliance with this Ordinance and any conditions herein,
Cascade Township may require reasonable performance guarantees, as
authorized under the Township Rural Zoning Enabling Act to insure
completion of improvements such as, but not limited to, landscaping,
drainage, lighting, roads, and utilities. The Township Board,
Engineer, or Planning Director may require such guarantees at any time
they deem necessary to insure completion of the improvements.
Section VIII. Effective Date
This Ordinance shall become effective upon publication in The Grand
Rapids Press, a newspaper of general circulation within Cascade
Charter Township.
The foregoing Ordinance was offered by Board Member Henning,
supported by Board Member Parrish. The roll call vote being as
follows:
YEAS: Boonenberg, Carpenter, Henning, Julien and Parrish
NAYS: Hansen
ABSTAIN: None
ABSENT: Champion
Brenda J. Henning
Cascade Charter Township Clerk
CERTIFICATION
I hereby certify the foregoing to be a true copy of an Ordinance
adopted at a Regular Meeting of the Cascade Charter Township Board on
the 14th day of October, 1992.
Brenda J. Henning
Cascade Charter Township Clerk

Government
~ Departments ~
Community
Business ~
Reference Desk ~
What's Happening
Help ~
Home ~ Search ~ Site Map
Comments? Feedback? Questions? Click here to send an email.
Site Use Policy
This page last modified
06/08/04.
All information © 2003-2004Cascade Township, Michigan
|
Site
Design/Development by
 |
|