2025 Road Improvements
.png.aspx?width=900&height=588)
Kent County Road Commission 2025 Improvements
Location: Various streets throughout the Township
Estimated Completion: Fall 2025
Funding Source: Funded by the Township General Fund and Kent County Road Commission
The Kent County Road Commission works with Township Staff to develop a road improvement plan each year and have have planned the following for 2025:
Bridge Rehab
 |
 |
48th Street over Thornapple River |
|
Bridge Preventative Maintenance
 |
 |
Thornapple River Drive over CSX Railroad |
36th Street, 0.4-miles northwest of Thornapple River Drive |
 |
36th Street, 500-feet east of Kraft Avenue |
Mill and Fill
28th Street – Kraft Avenue to Cascade Road
 |
Project Dates: 6/16/2025-6/27/2025
Conctractor: Michigan Paving and Materials
Emergency Numbers:
Road Work: 616-570-4059
Traffic Control: 616-570-4059
KCRC Personnel:
Sean McKean, Project Engineer
Maher Almunayr, On-Site Inspector
Scope of Work: Cold milling 28th Street to a depth of 2” and paving back with a fiber reinforced HMA mix followed by permanent pavement markings. This project will be completed while maintaining two-way traffic for the duration of project.
|
 |
|
For further questions related to the Burton St Bridge, contact Engineer Thorne at (616) 949-1500 or email him at athorne@cascadetwp.com.