Whitneyville Avenue Road Work

| Posted in: Latest News

Road: Whitneyville Avenue


Limits: I-96 overpass to Cascade Road

Schedule (subject to change):
  • September 20 - October 16, 2021
Traffic Control: 
  • Closed to through traffic
  • Detour posted
Contractor: Rieth-Riley

Cost: $350,000

About: This pavement replacement project includes both full-depth cold milling and crushing and shaping existing asphalt. Two courses of hot mix asphalt will then be applied. 


 