Landscape

Pathway Improvements
Location: Burton St and Spaulding Ave
Completed: Week of 6/10/24
Funding Source: Pathways Fund

Repaving of the Burton St and Spaulding Ave stretches of pathway was completed 5/22/24.  The contractor placed ADA-compliant concrete sidewalk ramps on 5/27/24. Restoration of topsoil and grass seed followed the week of 6/3/24.  With the final traffic control devices removed and the pathways formally reopened the week of 6/10/24.
 
Cascade Village Sidewalk Repair
Location: Various cracks and trip hazards in the Village District
Completed: 5/30/24
Funding Source: 50% DDA and 50% Township General Fund

All concrete was successfully placed 5/21/24, the contractor restored and made final touches on 5/20/24. The sidewalk was opened for public use on 5/20/24.